self-sufficiency.The pipeline will enable the transportation of non-conventional gas from Vaca Muerta to the province of Buenos
(Photo Internet reproduction)Oscar Sardi, CEO of Transportadora Gas del Sur (TGS), anticipates the pipeline will take about a month to
US$361,301 million will be needed for its completion.The pipeline is projected to enhance the current gas transportation capacity by 11
million m3/day, leading to an annual foreign currency saving of US$2.249 billion.The government predicts the project will be 100% complete
by November 2023.By July, the pipeline is expected to add 10 million m3/d to the transport capacity, followed by an additional 19 million
m3/d by autumn 2024 and another 18 million m3/d by winter 2024.This would result in a total capacity increase of 58 million m3/d, resulting
in a foreign currency saving of US$7.461 billion.