12 years on Tamor bridge construction yet to complete

INSUBCONTINENT EXCLUSIVE:
TERHATHUM, DECEMBER 18 Construction of a concrete bridge over the Lubughat-based
Tamor River has yet to be completed as 12 years have elapsed since its contract signing.
400 KV transmission line contract
under MCC scrapped
In Hamas' horrific killings, Israeli trauma over the
Holocaust resurfaces The construction of the
bridge linking Terhathum and Panchthar districts has not gained momentum
It is uncertain how long it will take to complete construction of the bridge.In the absence of the construction of the bridge, the residents
of Kummayak of Panchthar have to walk seven to eight hours a week carrying materials on their backs to reach Friday Hatia at Myanglung of
Tehrathum
From Myanglung of Tehrathum to Dharan, one has to travel 116 kilometers through Basantapur, Sidhuwa, Hile and Dhankuta
After the construction of the bridge, Dharan can be reached directly through Tamor corridor within half of its time
Hatia is near Kummayak Rural Municipality in Panchthar district
The goods produced in the village are taken to the Friday Hatia of Myanglung for sale. One has to return home with soap,
salt, oil, clothes and clothes on one's back from Myanglung.Ramesh Thapa, who had come to sell almonds from Bijuwapani of Kummayak rural
municipality to Myanglung Friday Hatia, said, "We thought that we would not have to carry a heavy load on the hill if the bridge was
constructed."A contract was signed with Swachchhanda Contractor Company in June 2011 for the construction of the bridge at a cost of Rs 130
million
The agreement was to complete the construction of the bridge by July 2018
Chief of the Road Division Office, Dhankuta, Ram Kumar Dev, said only 50 percent of the work of the bridge, which is 3 meters wide and 157
meters long, has been completed so far
Out of the five pillars, only four have been constructed
We are extending the construction deadline till mid-July 2024", he said.Contractor company's representative Ajay Lamichhane said that there
was no road leading to the bridge from Myanglung when the construction of the bridge started and it took time to dig the road.Arjan Dhungana
of Myanglung and Dik Bahadur Karki of Laligurans municipality had lodged a complaint with the Commission for the Investigation of Abuse of
Authority (CIAA)
Local residents of Myanglung have been putting pressure on the Myanglung Municipality and the District Administration Office, Tehrathum, by
forming a committee to press for the construction of the bridge at Tamor.
This article first appeared/also appeared in https://thehimalayantimes.com